3 Installation and setup
This section provides instructions for installing and commissioning the 700XA.
Installing a 700XA involves the following steps:
1. Observing precautions and warnings.
2. Planning site location and mounting arrangement.
3. Obtaining supplies and tools.
4. Mounting the unit.
5. Installing GC wiring.
6. Installing GC sample and gas lines.
7. Purging carrier gas lines.
8. Purging calibration lines.
9. Performing leak checks.
10. Starting up GC system.
3.1 Precautions and warnings
WARNING!
Install and operate all equipment as designed and comply with all safety requirements. The
seller does not accept any responsibility for installations of the GC, or any attached equipment,
in which the installation or operation thereof has been performed in a manner that is negligent
and/or non-compliant with applicable safety requirements.
WARNING!
If the unit is not operated in a manner recommended by the manufacturer, the overall safety
could be impaired.
WARNING!
The unit is intended to be connected to supply mains by qualified personnel in accordance with
local and national codes.
WARNING!
A suitable APPROVED switch and fuse or a circuit breaker shall be provided to facilitate the
disconnection of mains power.