T400 Calibration Procedures T400 Ozone Analyzer Operator’s Manual
190
9.3. MANUAL CALIBRATION CHECK AND CALIBRATION WITH
VALVE OPTIONS INSTALLED
9.3.1. SETUP FOR CALIBRATION CHECKS AND CALIBRATION WITH
VALVE OPTIONS INSTALLED.
Connect the sources of zero air and span gas as shown in Figure 9-2 and Figure 9-3.
Enclosure Wall
Figure 9-2: Gas Line Connections for the T400 Analyzer with Zero/Span Valve Option (OPT-50A)
06870C DCN6332