11. POSITIONING DEBUGGING
HELPFUL OPERATION (1)
To carry out the interpolation control test operation, perform the following
operation.
1. Perform the basic operation steps 1 to 4 to display the Position data test set
dialog box.
2. Select "Position data No." in Condition in the Position data test set dialog box.
3. Set the reference axis and positioning data No. of interpolation control to Start
point in the Position data test set dialog box.
4. When you have set the start point, move the cursor to the top line and make
sure that "1" appears in Start No.
5. Click the "OK" button.
6. Click the "Start" button in the Test start/set dialog box.
At this time, test operation is started with the positioning data No. of the axis set
to Start No. "1".
7. To end the positioning data test, click the "Exit" button.