Using the Mounting Template
The mounting template (see insert)isdesignedtosimplifymountingtheoperator.Itprovidestheinstallerwith
theproperlocationsforrunningpowerandaccessorywiringconduits.Thetemplateisalsomarkedwiththe
correctdistancebetweentheoperatormountingholesandshowstheinstallerhowtopositiontheoperatorfor
thecorrectclearancebetweenthehousingandthegate.
NOTE: The operator must be securely mounted on a level concrete pad. If you do not have an existing pad to work
with, be sure to install wiring conduit before pouring concrete. You must use (5)
3
/8” diameter wedge type mounting
anchors, washers, and nuts (not included) to mount the operator on the pad.
Study the mounting template. Lay the mounting template on the level concrete pad and mark the pad according
to the instructions on the template.
Before mounting the operator, check the following:
•Theconcretepadislevel. 
•(6)3/8”diametermountinganchorsareintheircorrectpositions.
•Conduitforpowerandaccessorywiringisinstalled.
16 in
(45.7cm)
16 in
(45.7 cm)
30 in
(76.2 cm)
MINIMUM
BELOW GROUND LEVEL
Mounting Operator
Concrete mounting pad 16 in x 16 in. Consult local building codes for depth below
ground level. Absolute minimum depth 30 in (76.2 cm) below ground level.
Use 3/8 in (.95 cm) diameter concrete mounting bolts in mounting pad.
10 in
(25.4 cm)
33 in
(83.8cm)
TO BASE
GROUND LEVEL
6 / in
(16.2 cm)
3
8
4 / in
(16.2 cm)
5
8
6 Concrete
Mounting Bolts
3/8” diameter