HP (Hewlett-Packard) c7000 Doll User Manual


 
Cabling and powering up the enclosure 62
minutes to power up, while an enclosure with fewer blades might take less time. Server blades are powered
up incrementally, starting from device bay 1.
When first initialized, the Onboard Administrator programs the mezzanine cards on the blades during
discovery. After the mezzanine cards are programmed, powering up the enclosure takes only 1 to 2 minutes.
The enclosure and the Insight Display now have power. Configure the enclosure ("Running the Insight Display
installation steps" on page 65) using the Insight Display.
PDU installation
The PDU can be installed in either a 1U or a 0U configuration. For more information about installing the PDU
in the rack, see the installation instructions that came with the PDU.
IMPORTANT: Rack-based single-phase PDUs cannot be used with a three-phase power
configuration.
IMPORTANT: Total VA load of the attached enclosures should not exceed the VA capacity of the
PDU. Do not exceed the rated current on circuit breakers.
To connect power to the PDU:
1. Connect the AC power cables to the power connectors on the rear of the enclosure corresponding to the
power supply that was populated on the front of the enclosure.