5 Startup Checklists
5-1 Introduction
Important!
These lists assume the installation information
in this manual has been read and followed.
Have new chillers started up and checked
by a qualified refrigeration service technician.
Sterling offers factory startup for SSC Series Series chilling stations.
Call the Sterling Service Department
at 1 (800) 233-4819 for more details.
5-2 Water-Cooled SSC Series Startup Checklist
þ Check the shipping papers against the serial tag to be sure
chiller size, type and voltage is correct for the process.
þ Check the transformer primary voltage connections to be sure
they are configured for the electrical power you are using.
þ The voltage at the main power connection must be within plus
or minus ten percent (±10%) of the voltage listed on the serial
tag.
þ Phase imbalance must be less than two percent (<2%).
þ Electrical connections must conform to all applicable codes.
þ Complete the chilled water TO and FROM PROCESS
connections.
þ The optional or field installed chilled water supply and return
valves on the chiller must be open.
þ Be sure the pump tank and chilled water circuit are filled with a
water/glycol mixture that provides freeze protection to 20°F
(12ºC) below the leaving water temperature you want.
þ Complete the tower or city condenser WATER IN and WATER
OUT connections. Provide an adequate condenser water
supply; 2 gpm per ton for city water or 3 gpm per ton for tower
water operation.
þ Remove all tools, foreign matter and debris from the pump
tank reservoir and piping.