6. Reinstall the rear PDCA bezel.
CAUTION: Do not measure voltages with the PDCA breaker set to ON. Make sure the
electrical panel breaker is ON and the PDCA breaker is OFF.
7. Plug in the PDCA connector.
8. Check the voltage at the PDCA:
a. Using a T-20 driver, remove the screw on the hinged panel at the top of the PDCA.
(Figure 3-29).
b. Using a voltmeter, measure the test points and compare the values to the ranges given
in Table 3-3 (page 87) to make sure the voltages conform to the specifications for the
PDCA and local electrical specifications.
If the voltage values do not match the specifications, have the customer contact an
electrician to troubleshoot the problem.
Figure 3-29 Checking PDCA Test Points (5-Wire)
Table 3-3 4- and 5-Wire Voltage Ranges
5-Wire4-Wire
L1 to N: 200-240 VL2 to L3: 200-240 V
L2 to N: 200-240 VL2 to L1: 200-240 V
L3 to N: 200-240 VL1 to L3: 200-240 V
N to Ground:
1
1 Neutral to ground voltage can vary from millivolts to several volts depending on the distance to the ground/neutral
bond at the transformer. Any voltage over 3 V must be investigated by a site preparation or power specialist.
Setting Up the System 87