6 Mounting Preparing for mounting
© 2007 Moog GmbH User Manual RKP-II (CA53461-001; Version 1.0, 10/07) 33
6 Mounting
Mounting
6.1 Preparing for mounting
Preparing for mounting
Procedure:
1. Pump has been unpacked.
Ö Chap. "5.1 Unpacking the Pump", Page 29
2. The required supplementary documentation is at hand.
3. The hydraulic plans from the machine / equipment manufacturer have
been made available.
4. The required standard tools and mounting material are at hand.
For pumps in explosive areas, the supplementary documentation should
also be observed: Ö User Manual RKP II Explosion-Proof
For any and all tasks to be performed on the pump, suitable personal
protective equipment should be worn.
Ö Chap. "2.2.4 Work Safety", Page 9
DANGER Risk of injury and property damage as a result of leaking
operating fluid!
Any operating fluid that sprays out under high pressure
because of improper mounting may lead to serious injury or
property damage.
Only trained personnel should be allowed to mount the
pump.
Check the cleanliness of the mounting surface.
Observe the tightening torques for the fasteners.
Ö Chap. "12.4 Tightening Torque", Page 65
Use only specified fasteners (quantity/type).
Make sure the proper flange and screws are being used
as per standard (e. g. SAE).
Check for the existence and use of the proper O-rings.
Use the correct sealant based on the operating fluid.
Mount all connections to be hydraulically sealed.
Do not exceed the maximum operating pressure in the
system.
Do not exceed the maximum body pressure.
DANGER Serious bodily injury!
Starting-up the machine/equipment during the mounting
process may lead to serious bodily injuries or death.
Make sure that the machine/equipment cannot be
switched on.
The pump is pre-assembled at the factory.