Installation and Set-Up (Continued)
4. Pneumatic Connection
The case former requires a 5.2 bar gauge
pressure [75 PSIG], 6.0 m
3
/h @ 21°C, 1.01 bar
[3.5 SCFM] compressed air supply.
The customer supplied air supply hose should
be connected to the barbed fitting on the On/Off
valve and clamped tightly with the hose clamp
provided. See Figure 2-3. Shut the air valve off
and connect the air line. Turn the On/Off valve
On (SUP), to energize the pneumatic
components.
If another type of connector is desired, the
barbed fitting and/or elbow can be removed and
replaced with the desired connector. The air
On/Off valve inlet is 1/4-18 standard pipe
threads.
5. Side Guide Extensions
Under certain circumstances, the centering
guides may interfere with the side guides on the
100a, 200a or 700a case sealers. If this occurs,
the case sealer side guides can be removed and
centering guide extensions can be installed on
the 300cf Case Former. The side guide
extensions are included with the 300cf. Install
guides as shown in Figure 2-4.
6. After completing the "Installation and Set-Up"
procedure, continue through "Operation" to be
sure case former is properly set-up to run boxes.
Figure 2-3 – Pneumatic Connections