START-UP CHECKLIST
MODEL NO.:
SOFTWARE VERSION (SEE FIG. 11)
DATE:
SERIAL NO.:
TECHNICIAN:
PRE-START-UP:
Ⅺ VERIFY THAT DIP SWITCH SETTINGS ARE CORRECT
Ⅺ VERIFY THAT ALL PACKING MATERIALS HAVE BEEN REMOVED FROM UNIT
Ⅺ REMOVE ALL SHIPPING HOLDDOWN BOLTS AND BRACKETS PER INSTRUCTIONS
Ⅺ VERIFY INSTALLATION OF ECONOMIZER HOOD
Ⅺ VERIFY INSTALLATION OF ALL OPTIONS AND ACCESSORIES
Ⅺ VERIFY THAT CONDENSATE CONNECTION IS INSTALLED PER INSTRUCTIONS
Ⅺ VERIFY THAT ALL ELECTRICAL CONNECTIONS AND TERMINALS ARE TIGHT
Ⅺ CHECK GAS PIPING FOR LEAKS
Ⅺ CHECK THAT INDOOR-AIR FILTERS ARE CLEAN AND IN PLACE
Ⅺ VERIFY THAT UNIT IS LEVEL WITHIN TOLERANCES
Ⅺ CHECK FAN WHEELS AND PROPELLERS FOR LOCATION IN HOUSING/ORIFICE, AND VERIFY SETSCREW
IS TIGHT
Ⅺ VERIFY THAT FAN SHEAVES ARE ALIGNED AND BELTS ARE PROPERLY TENSIONED
Ⅺ VERIFY THAT SUCTION, DISCHARGE, AND LIQUID SERVICE VALVES ON EACH CIRCUIT ARE OPEN
START-UP:
ELECTRICAL
SUPPLY VOLTAGE L1-L2
L2-L3 L3-L1
COMPRESSOR AMPS — COMPRESSOR NO. 1 L1 L2 L3
— COMPRESSOR NO. 2 L1 L2 L3
SUPPLY FAN AMPS EXHAUST FAN AMPS
TEMPERATURES
OUTDOOR-AIR TEMPERATURE F DB (Dry Bulb)
RETURN-AIR TEMPERATURE
FDB F WB (Wet Bulb)
COOLING SUPPLY AIR
F
GAS HEAT SUPPLY AIR
F
PRESSURES
GAS INLET PRESSURE
IN. WG
GAS MANIFOLD PRESSURE STAGE NO. 1
IN. WG STAGE NO. 2 IN. WG
REFRIGERANT SUCTION CIRCUIT NO. 1
PSIG CIRCUIT NO. 2 PSIG
REFRIGERANT DISCHARGE CIRCUIT NO. 1
PSIG CIRCUIT NO. 2 PSIG
Ⅺ VERIFY REFRIGERANT CHARGE USING CHARGING CHARTS ON PAGE 31
CL-1